Our website use cookies to improve and personalize your experience and to display advertisements(if any). Our website may also include cookies from third parties like Google Adsense, Google Analytics, Youtube. By using the website, you consent to the use of cookies. We have updated our Privacy Policy. Please click on the button to check our Privacy Policy.

The challenge to Oxford’s Olympic cost overrun study from 2000 to 2016 data

The challenge to Oxford’s Olympic cost overrun study from 2000 to 2016 data
Contents
  1. Summary
  2. What you will find here
  3. The cost overrun figure, challenged
  4. Comparing against whoever lost the vote
  5. The tourism legacy
  6. Sochi, with all its figures
  7. What the literature says as a whole
  8. Why cities keep bidding
  9. How to handle this, practically speaking
  10. Frequently asked questions
  11. What we do not know
  12. References

There are two figures in circulation about the Olympic Games and both deserve examination. The first is the cost overrun: a much-cited University of Oxford study put the average deviation from Olympic budgets between 1960 and 2012 at 179% in real terms and 324% in nominal terms. The second is the benefit: the economic boost that justifies the bid.

What makes this instance fascinating is that each has faced scrutiny using empirical figures. A re-examination released in 2022 failed to duplicate the findings of the Oxford study covering the 2000-2016 timeframe, instead registering direct investment cost overruns ranging from 13% to 178%, while also pointing out that total expenses for the Games account for under 0.28% of the host nation’s GDP. Furthermore, when evaluated against the proper benchmark — those municipalities that competed for the Games but were unsuccessful — the advantage emerges as 3 to 4 percentage points of regional GDP during the hosting year and the preceding one, alongside long-term impacts that lack statistical robustness.

And one specific case no discussion should omit: Sochi 2014 cost $55 billion, 4.5 times the bid budget, with 96.5% public funding and a subsequent annual burden of around $1.2 billion.

Summary

It is worth checking in each row whether the event year or the long run is being measured, and whether the subject is Summer or Winter Games. Those are four distinct cases and the results do not coincide.

Finding Result Study and year
Average cost overrun per the Oxford study 179% real and 324% nominal, 1960-2012 Schmidt (2017)
The same calculation, re-analysed with more official data 13% to 178% on direct investments, 2000-2014 Preuss, IJSPP (2022)
Weight of the Games’ cost against national GDP Less than 0.28% Preuss, IJSPP (2022)
Effect on regional GDP, Summer Games +3 to +4 points in the event year and the one before Firgo, RSUE (2021)
Effect of the Winter Games None positive; if anything, a temporary decline Firgo, RSUE (2021)
Long-run effect against runner-up cities None in population, GDP per capita or trade openness Billings and Holladay, EI (2012)
Short-run tourism legacy across nine cities Little evidence to support it Moss, Gruben and Moss, JPRTLE (2019)
Total cost of Sochi 2014 $55 billion, 4.5 times the initial budget Müller, EGE (2014)
Share of public money in Sochi 96.5%, the highest on record Müller, EGE (2014)
Overall conclusion of the economic review A money-losing proposition in most cases Baade and Matheson, JEP (2016)

What you will find here

• The world’s most-cited cost overrun figure and why a re-analysis could not reproduce it.

  • What happens when the host city is compared against the city that lost the vote.

• Why the Summer and Winter Games produce opposite results.

  • What remains of the tourism heritage when evaluated through air passenger statistics.
  • The Sochi case, complete with all its figures.

• Why, this being what the literature says, cities keep submitting bids.

The cost overrun figure, challenged

Start with the one everyone cites. Sascha Schmidt summarised it in 2017 — in a book chapter, rather than a peer-reviewed article — using the phrasing that has since become standard: between 1960 and 2012, the Olympic Games consistently exceeded their budgets, averaging a 179% overrun in real terms and 324% in nominal terms, as uncovered by researchers at the University of Oxford.

His complementary observation describes the state of the debate well: although politicians and interest groups continually justify the overarching costs by promising future economic benefits, economists have a hard time finding any economic impact from hosting the Games when engaging in ex post analysis of indicators like GDP, employment rate and trade volume.

Back in 2022, Holger Preuss from Johannes Gutenberg University Mainz re-evaluated that figure within the pages of the International Journal of Sport Policy and Politics. It is important to be clear regarding the exact nature of this piece: a commentary and methodological dispute, rather than an independent measurement, while his extensive background working inside the Olympic realm forms part of the background to his stance.

That said, his objections are concrete and checkable. He starts from the fact that the so-called Oxford study shows cost overruns of 170% to 750% with a substantial risk of further overruns in future, and sets out to re-analyse them using a method in accordance with the international convention of comparing across time and geographies, with a dataset containing abundantly more governmental data.

His results: he could not replicate the Oxford study’s results for the period 2000-2016. His own calculation yields, for the Games from 2000 to 2014 and for direct non-organising-committee investments, cost overruns in the range of 13% to 178%. And he adds the figure that sets the discussion in macroeconomic scale: the costs of the Olympic Games represent less than 0.28% of GDP; hence it is clear that the Games cannot cause a severe national economic crisis.

Preuss additionally outlines six common misconceptions within this discourse and challenges the notion that host cities issue a blank cheque to the International Olympic Committee, pointing out that requirements are established within the Host City Contract. The vast gap between the two estimates — 170-750% versus 13-178% — does not mean one is inaccurate while the other is correct; rather, it highlights that the outcome relies entirely on which specific expenditures are classified as event costs. Ultimately, that bookkeeping choice remains the core of the debate in practice.

Study What it measured What it found What it cannot establish
Schmidt (2017) Summary of the Oxford study 179% real and 324% nominal, 1960-2012 Book chapter; not an original measurement
Preuss, IJSPP (2022) Re-analysis with more governmental data 13% to 178% on direct investment Commentary and method dispute, not new measurement
Firgo, RSUE (2021) Hosts against runners-up in the vote +3 to +4 points in the event year Long run positive but not robust
Billings and Holladay, EI (2012) Hosts matched with finalists, 1950-2005 No long-term effect Does not rule out non-economic effects
Boto-García and Santana-Gallego (2025) Panel 1991-2023, dynamic differences Notable effects on employment and GDP per capita National aggregate; no regional breakdown
Müller, EGE (2014) Costs and impacts of Sochi 2014 $55 billion and a $1.2 billion annual burden An extreme case in a singular political context

Comparing against whoever lost the vote

The core methodological flaw within this research field becomes apparent immediately upon identification: the municipalities chosen to stage Olympic Games are far from typical. They submit bids precisely because they possess high ambitions, robust growth, strong financial standing, and solid political backing, factors that independently shape their economic landscapes. Pitting an Olympic host city against national averages wrongly attributes inherent municipal traits to the event itself.

The elegant solution exists and two studies have used it: comparing against the cities that also bid and lost. They are cities with the same ambition and the same profile, minus the event.

Matthias Firgo applied it in Regional Science and Urban Economics in 2021 to examine both immediate and long-term impacts on the regional economy, utilizing runners-up in the Olympic bidding process to construct the counterfactual for Olympic host regions.

His results, by type of Games:

Case Short-run effect Long-run effect
Summer Games +3 to +4 points of regional GDP per capita above the national level Positive but not statistically robust
Window of the Summer effect The event year and the one before Does not clearly persist
Winter Games No positive impact on the host region No documented effect
Winter Games, strict reading If anything, a temporary decline in regional GDP per capita No subsequent compensation
Seven European Games, independent analysis Summer: positive in the post-event phase Winter: no significant positive results
Hosts against finalists, 1950-2005 Not assessed separately No effect on population, GDP or trade

The final row corresponds to Stephen Billings and Scott Holladay, who published in Economic Inquiry in 2012 the toughest study in this group. Their design: matching Olympic host cities with cities that were finalists for the Games but were not selected by the International Olympic Committee, and applying a difference-in-differences estimator to examine post-Olympic impacts between 1950 and 2005.

Their result, literally: regression results provide no long-term impacts of hosting an Olympics on two measures of population, real gross domestic product per capita and trade openness.

It is important to read exactly what that means and what it does not. It does not say the Games have no effect: it says that twenty or fifty years later, the host city is indistinguishable from the city that lost the vote on those four variables. The structural economic legacy, measured that way, does not appear.

What the most recent measurement does find

David Boto-García and María Santana-Gallego published in Tourism Management in 2025 the analysis with the most modern econometric apparatus: a panel from 1991 to 2023 with dynamic difference-in-differences estimators that distinguish anticipation from legacy effects, account for staggered treatment timing and accommodate heterogeneous effects.

Their outcomes outshine previous ones and ought to be documented: moderate anticipatory effects on tourism and notable impacts on employment and GDP per capita, with the Summer Games exhibiting a stronger impact.

The authors frame their contribution by flagging precisely the field’s problem: empirical evidence on the overall impact remains inconclusive, largely due to methodological challenges, and they highlight the limitations of standard approaches. That a better method yields a more positive result is relevant and has to await replication.

The tourism legacy

The tourism argument is the second pillar of any bid: the world sees the city and then comes to visit it. Steven Moss, Kathleen Gruben and Janet Moss tested it in Journal of Policy Research in Tourism, Leisure and Events in 2019 with the most direct data possible: monthly international air passenger arrivals for nine Olympic host cities, with a time series methodology controlling for problems noted in prior studies — pre-existing trends, external events, seasonality and crowding out.

Their outcome: the data reveals minimal backing for the legacy impact over a brief timeframe.

Two studies on Brazil and on major events in general qualify that conclusion in a more favourable direction. Roberto Meurer and Hoyêdo Nunes Lins analysed in Tourism Economics in 2018 the effects of the 2014 World Cup and the 2016 Games on Brazilian international travel receipts, and Christian Vierhaus, in the same journal the same year, estimated the international tourism effect of hosting Olympic Games and FIFA World Cups. Their results point to detectable tourism effects, which is not incompatible with the absence of legacy measured in the airport data: an effect can exist in receipts and not in passenger volume, or concentrate in the event period.

Eleni Kasimati and Peter Dawson supplied for Athens 2004 the temporal pattern that sums up this entire literature, with an aggregate macroeconometric model published in Economic Modelling in 2008. They find evidence that the Games can successfully boost the host city’s economy by generating benefits that outweigh the preparation cost. And they add the coda: whilst the impact effects are quite strong during the preparation phase and the year the Games took place, the long-term economic legacy effects appear to be quite modest.

Strong during preparation and the event, modest afterwards: that is exactly the profile Firgo finds using finalists as the counterfactual, and it is compatible with Billings and Holladay’s long-run zero. Three studies, three methods, the same curve.

Sochi, with all its figures

Martin Müller published the financial records of the Sochi Winter Games in Eurasian Geography and Economics back in 2014, establishing what remains the most comprehensively documented instance across the entire academic literature. It is worthwhile to present these numbers plainly and without embellishment:

Item Figure
Total cost $55 billion
Budget at the time of the bid $12 billion
Cost overrun multiplier 4.5 times
Sports-related costs Around $16 billion
Ranking by sports-related cost Second-most expensive Games ever
Ranking by cost per event The most expensive ever held
Share of public funding 96.5%, the highest on record
Estimated subsequent annual burden Around $1.2 billion a year

And the outcome equation: the rewards brought by such a steep price remain constrained. Massive building sprees triggered excessive hotel availability, financial backers failed on government-guaranteed debt, and a cohesive strategy for repurposing the facilities alongside several major infrastructure works is missing.

The annual burden Müller quantifies includes operation, maintenance, and foregone interest and tax revenue. And the two non-economic effects usually invoked do not appear either: the event also did not manage to improve the image of Russia in the world, and among the domestic population support dropped over the seven years of its implementation, most notably among the local population.

That last observation deserves underlining. Support fell most among those living where the Games were held. The supposed civic pride, which is the argument of last resort when the economic ones fail, behaved the other way round.

What the literature says as a whole

Two reviews allow everything above to be placed. The most cited is by Robert Baade and Victor Matheson in Journal of Economic Perspectives in 2016, and it sorts costs and benefits into three categories each. The costs: general infrastructure such as transportation and housing, specific sports infrastructure required for competition venues, and operational costs including general administration as well as the opening and closing ceremony and security. The benefits: the short-run benefits of tourist spending during the Games, the long-run «Olympic legacy» — infrastructure improvements and increased trade, foreign investment or subsequent tourism — and intangible benefits such as the «feel-good effect» or civic pride.

Their conclusion is the most-quoted sentence in the field: the overwhelming conclusion is that in most cases the Olympics are a money-losing proposition for host cities; they result in positive net benefits only under very specific and unusual circumstances. And they add a relevant asymmetry: the cost-benefit proposition is worse for cities in developing countries than for those in the industrialised world.

The 2018 study by Pasquale Scandizzo and Maria Rita Pierleoni, published in Journal of Economic Surveys, broadens the perspective on the Games by viewing them as cultural assets and catalysts for endogenous growth, while also reviewing various methodologies, concepts, and approaches. According to the authors, their broad conclusions are controversial, with some hints of positive overall effects, but also with a well-documented tendency to exaggerate the benefits and underestimate the costs in the ex ante versus the ex post studies.

And one observation that opens a door: ex post cross-country econometric studies tend to catch sizeable differential and persistent benefits ignored by individual studies. That is to say, the method of measurement partly determines the result, just as it did with the cost overrun.

Sorted by category of inquiry, the existing body of work proves significantly less contradictory than it initially appears.

Question Soundest answer Degree of agreement
Do budgets overrun? Yes, invariably; the exact scale remains the subject of debate Absolute consensus
Is there a boost in the event year? Indeed: +3 to +4 points during summer Strong
Is there a long-run economic legacy? None, when compared to runner-up cities High, barring one recent exception
Is there a tourism legacy? Scant evidence initially Moderate: varies by metric
Is summer the same as winter? Negative: winter yields no favorable impact Strong
Is it the same in rich and poor countries? Different: poorer nations suffer worse outcomes Strong

What that table shows is that the real disagreement concentrates in a single cell — the magnitude of the cost overrun — and in the exception of the 2025 measurement. On everything else, twenty years of work using different methods point to the same curve: a peak in the event year and little or nothing afterwards.

Why cities keep bidding

If the overwhelming conclusion is that it is a money-losing proposition, the obvious question is why cities compete for it. Baade and Matheson pose it explicitly in closing their review: they discuss why what looks like an increasingly poor investment decision on the part of cities still receives significant bidding interest, and whether changes in the bidding process of the International Olympic Committee will improve outcomes for potential hosts.

Schmidt points the same way in noting that politicians and interest groups justify the overrunning costs with promises of future benefits. And Müller supplies the fact that changes the politics of this question: in Sochi, public support fell over the seven years of implementation, and more sharply among local residents. Preuss, in his 2018 article in the same journal, had proposed a legacy measurement framework precisely because, in his terms, while the sport organisations gain large revenues, cities lose, and the referendums held in the preceding years returned negative results consistently.

Put differently: for ten years, the economic literature and the voters in candidate cities have shared the same view, and bidding outcomes are determined elsewhere.

To be fair to the tender files, the literature does not claim the Games have zero impact. Rather, it notes that the event generates a substantial, brief, and intense surge of activity before steering the host city back to its prior path. For a municipality that desires a specific piece of infrastructure anyway—such as a subway line, a regenerated waterfront, or a transit hub—an Olympic deadline serves as a mechanism to complete construction in seven years rather than two decades. This tangible advantage is overlooked by these studies because it stems from an acceleration phenomenon rather than a direct Olympic consequence.

The candid formulation of the bid, therefore, is not «the Games will pay for themselves». It is «we are buying a deadline, and here is what the deadline will deliver», with the budget overrun factored in at whatever end of the 13-to-178 per cent spectrum the municipality can absorb. Such an argument is justifiable. It is likewise far more difficult to present to a public vote, a factor that perhaps explains why the referendums consistently collapsed.

How to handle this, practically speaking

  • Always ask which line items are in the cost. The difference between a 170-750% overrun and a 13-178% one is largely an accounting decision about what gets attributed to the event.
  • Demand comparison against the finalist cities. It is the only honest counterfactual, and with it the long-run effect disappears in population, GDP per capita and trade openness.

• Do not treat summer and winter as the same case. The Summer Games give +3 to +4 points in the event year; the Winter Games, no positive impact and possibly a temporary decline.

• Discount the tourism legacy. Air passenger data from nine host cities show little evidence supporting the short-run effect.

• Budget for subsequent maintenance, not just construction. Sochi carries around $1.2 billion a year in operation, maintenance and foregone revenue.

• Distrust pre-event studies. The 2018 review documents a tendency to exaggerate benefits and underestimate costs in ex ante studies relative to ex post ones.

Frequently asked questions

Are the Olympic Games profitable?

According to the most-cited review, no: in the majority of instances, they represent a financial drain for host municipalities, generating positive net gains exclusively under highly specific and exceptional conditions. Furthermore, this endeavor tends to yield even poorer outcomes within developing nations.

To what extent do budgets get exceeded?

It depends what is counted. The Oxford study puts the 1960-2012 average at 179% real and 324% nominal; a re-analysis with more governmental data could not replicate it for 2000-2016 and obtained 13% to 178% on direct investments.

Is there any real economic boost?

Indeed, and with distinct limits. Relative to runner-up cities, the Summer Games elevate regional per capita GDP by 3 to 4 percentage points higher than the nationwide figure during both the hosting period and the preceding year. The enduring impact remains positive, although lacking robust statistical significance.

And twenty years later?

The study matching hosts with finalists between 1950 and 2005 finds no long-term impact on two measures of population, real GDP per capita or trade openness.

Do more tourists come afterwards?

Monthly international air passenger arrival data for nine host cities show little evidence to support the short-run legacy effect. Other studies detect effects on travel receipts, which is not the same variable.

What happened in Sochi?

It cost $55 billion against the bid’s $12 billion, with 96.5% public money, left hotel overcapacity, defaults on state-backed loans and no coherent after-use plan, and carries around $1.2 billion a year in burden.

What about civic pride?

It serves as the ultimate recourse, and within the most thoroughly recorded instance, the dynamic unfolded inversely: support dropped over the seven years of implementation, most notably among the local population.

What we do not know

  • What the correct cost overrun is. The two estimates differ by an order of magnitude and the discrepancy is an accounting one: which general infrastructure items are attributed to the event.

• Why the more recent methods give more positive results. The 1991-2023 panel finds notable impacts on employment and GDP per capita where the finalist-based designs see none in the long run.

• Whether there is a city-size threshold below which it never pays. The asymmetry between developed and developing countries is documented; the threshold is not.

• What the intangible benefit is worth. Baade and Matheson include it as a category and nobody has quantified it comparably against the costs.

• Whether changes in the International Olympic Committee’s bidding process improve the outcome. That is the question closing the 2016 review and it remains empirically unanswered.

References

1. Baade, R. A. and Matheson, V. A. «Going for the Gold: The Economics of the Olympics». Journal of Economic Perspectives, 2016. 10.1257/jep.30.2.201

2. Scandizzo, P. L. and Pierleoni, M. R. «Assessing the Olympic Games: The Economic Impact and Beyond». Journal of Economic Surveys, 2018. 10.1111/joes.12213

3. Firgo, M. «The causal economic effects of Olympic Games on host regions». Regional Science and Urban Economics, 2021. 10.2139/ssrn.3500856

4. Billings, S. B. and Holladay, J. S. «Should Cities Go for the Gold? The Long-Term Impacts of Hosting the Olympics». Economic Inquiry, 2012. 10.1111/j.1465-7295.2011.00373.x

5. Preuss, H. «Re-analysis, measurement and misperceptions of cost overruns at Olympic Games». International Journal of Sport Policy and Politics, 2022. Commentary article. 10.1080/19406940.2022.2037685

6. Schmidt, S. L. «Hosting the Olympic Games». 2017. Book chapter. 10.1007/978-3-319-47458-8_51

7. Müller, M. «After Sochi 2014: costs and impacts of Russia’s Olympic Games». Eurasian Geography and Economics, 2014. 10.1080/15387216.2015.1040432

8. Boto-García, D. and Santana-Gallego, M. «Old questions, new methods: Revisiting the economic effects of hosting mega-sport events». Tourism Management, 2025. 10.1016/j.tourman.2025.105324

9. Moss, S. E., Gruben, K. H. and Moss, J. «An empirical test of the Olympic tourism legacy». Journal of Policy Research in Tourism, Leisure and Events, 2019. 10.1080/19407963.2017.1418750

10. Kasimati, E. and Dawson, P. «Assessing the impact of the 2004 Olympic Games on the Greek economy: A small macroeconometric model». Economic Modelling, 2008. 10.1016/j.econmod.2008.06.006

11. Vierhaus, C. «The international tourism effect of hosting the Olympic Games and the FIFA World Cup». Tourism Economics, 2018. 10.1177/1354816618814329

12. Meurer, R. and Lins, H. N. «The effects of the 2014 World Cup and the 2016 Olympic Games on Brazilian international travel receipts». Tourism Economics, 2018. 10.1177/1354816617746261

This article summarises peer-reviewed scientific literature on the economic impact of major sporting events, flagging in the text the book chapter and the commentary article included. The figures correspond to the editions and periods studied and are not extrapolable to any event. It is not public policy advice, nor an evaluation of any specific bid.

By Carla Villalba